This page describes how changes to LegalServer are tested, when they are released, and when they are effective on sites.

The release week runs from Thursday through Wednesday. Wednesday is the end of the current week's milestone and when final testing occurs.

The release notes are posted to the siteadmins mailing list on Wednesday night or Thursday morning.

Changes are Made and Committed
The developers work on tickets throughout the release week. Proposed code or database changes are developed and tested. Changes are reviewed by another developer. After passing initial review, changes are committed to a development branch of the code.

Final Testing
On Wednesday, we update a test copy of each site with all new changes. Each ticket is again tested by someone other than the developer who made the change. Support staff and developers participate in testing. Any issues that arise are either fixed and re-tested, or the change is rolled back for additional work in the next release week.

After ticket testing is finished, we run a series of unit tests. Each unit test checks a distinct piece of code or feature like "can a case profile be displayed", "can an event be created", etc.

After unit tests pass, we update test copies of 4 sites: a demo site, a site on the weekly update schedule, a site on the monthly update schedule, and an online intake site. Several of us then create an intake, open, close, and re-open a case, enter time, and run reports on each of those sites. For the online intake site, we do an application, transfer it, then review and accept it on the site it was transferred to. Any issues are dealt with, and if code changes are needed, the testing sites are update again and re-tested.

Sites are Updated
Overnight Wednesday, all demo sites are updated. Live sites on the weekly update schedule are not updated until overnight Thursday of the following week. We are testing the demo sites throughout that week as we work with current onboarding clients (who only have a demo site). Site administrators often check updates on demo sites during that week as well, particularly for new or changed features that are important for their site. Live sites on the legacy monthly update schedule are updated on Thursday night before the first Friday of the month. See the individual Release Notes for effective dates.

Immediate Fixes
There are sometimes fixes that can't wait for the regular update schedule. Internally we call these hotfixes, meaning an update is applied immediately to affected sites, or applied and affected sites updated overnight.